Scoping an outsourced arc flash study you can maintain in ETAP
Short answer
Anchor the scope on IEEE 1584.1-2013 and require data collection, short-circuit, coordination and arc-flash tasks in your own editable ETAP project. Accept no exclusion the contractor cannot tie to a documented basis, and treat 38 kA available against a 35 kA interrupting rating as an open overduty finding until verified utility data recalculates it.
On this page
- What does a complete arc flash study scope include?
- Why study coordination curves when the software already picks the tripping device?
- How much coordination does a 35-feeder radial system need?
- Which contractor shortcuts can the scope accept?
- Does load-flow analysis belong in the arc flash scope?
- What do we do about a 35 kA breaker the model shows at 38 kA?
- What deliverables and acceptance checks close the project?
- Questions asked
A scope worth signing anchors on IEEE 1584.1-2013, the IEEE guide for specifying scope and deliverable requirements for an arc-flash hazard calculation study, and it buys five things in order: data collection, a one-line model, a short-circuit study, protective-device coordination and the arc-flash calculation, delivered as an editable ETAP project your own staff can maintain. Coordination stays in, because the software only reports the device its model says will trip. And the 38 kA available against that 800 A breaker's 35 kA interrupting rating is an open overduty finding until verified utility data says otherwise; plant age retires nothing. The checklist below gives you the decisions to write into the document.
What does a complete arc flash study scope include? #
Five tasks in sequence: data collection, one-line modeling, short circuit, protective-device coordination and arc-flash calculation, delivered in your own editable ETAP project — the sequence IEEE 1584 lays out and IEEE 1584.1-2013 turns into scope and deliverable language. IEEE 1584-2018, the guide for performing arc-flash hazard calculations, supplies the incident-energy and arc-flash-boundary models and a nine-step process that begins with collecting electrical system data. NFPA 70E, Standard for Electrical Safety in the Workplace, 2024 edition, is where the arc-flash risk assessment your labels feed lives; confirm how these documents apply at your site with the authority having jurisdiction and the equipment documentation.
Write these requirements into the scope:
- The contractor builds and runs the study in your company's ETAP project, under your license, and hands over the editable model at the end — not PDFs of results.
- Data collection covers utility fault data, transformer nameplates (kVA, impedance, voltage — nameplate values, not typical values), conductor types, sizes and lengths, protective-device frames and settings, and motor lists.
- The 2018-model inputs are collected too: electrode configuration, enclosure size and bus gap at each analyzed location, because all three move incident energy and the arc-flash boundary.
- Every input lands in a register that separates field-verified values from assumptions.
- Short circuit runs for each operating configuration the plant actually uses, including any local generation — the case behind handling generator fault-current decay in arc-flash studies.
Why study coordination curves when the software already picks the tripping device? #
Because the module reports which device its model calculates as clearing, not whether that device is the one nearest the fault — without coordination, an upstream device can clear instead, and its longer clearing time raises incident energy at the bus you labeled. That answer is an output, not a verification. Coordination review is the check that the nearest device actually does the job, and it covers what the automatic pick does not:
- Main-versus-feeder behavior on each bus, so a feeder fault does not take the main.
- Transformer primary devices sitting above the inrush point — the check behind estimating transformer inrush current for protection coordination.
- Instantaneous overlap between molded-case breakers in series, which is common and gets documented rather than argued away.
Which device sets the clearing time is also the whole decision behind which breaker sets MCC arc-flash duration — the reason coordination stays in the scope.
How much coordination does a 35-feeder radial system need? #
Every source-to-load path gets a reviewed time-current curve, but you control cost by grouping: paths sharing the same breaker frames, settings, conductor sizes and lengths can be represented by one curve, with the report mapping every covered path to it. A sample scope that studies only the utility-to-main path, the largest feeder and the largest branch device is three curves, not a coordination study — the rest of the board stays unverified.
Put this rule in the scope:
- Every path from the source to the final protective device appears in its own time-current curve or in a documented group.
- A group is valid only where frames, trip settings and conductor sizes and lengths match; otherwise the path gets its own curve.
- If cost still forces cuts, the omitted paths are listed by name and reported as selective coordination unverified — never silently dropped.
Which contractor shortcuts can the scope accept? #
Accept short-cable and cord approximations when they are logged and justified; reject the small-transformer exclusion outright, and turn the small-motor exclusion into aggregation — each shortcut below carries its decision.
- Cables 10 ft and shorter: acceptable only for jumpers between adjacent gear in one lineup, where the dropped length is trivial against the total source-to-fault path. There is no 10 ft rule inside the study software — it is a convention, so the exclusion register carries every dropped cable with its size and length.
- SOW cord modeled as equal-AWG THHN: acceptable for this study, because resistance per length follows copper area; log it in the assumptions, since stranding and insulation differ.
- VFD contribution ignored: acceptable only for drives with a non-regenerative front end and no bypass contactor. Where a bypass can put the motor across the line, that motor contributes and stays in the model.
- Transformers below 112 kVA ignored: reject. That figure matches a catalog transformer size, not a standard threshold; the screening language that circulated with the 2002 edition of IEEE 1584 was 125 kVA and smaller at 240 V and below, and the 2018 edition did not keep it as a blanket exclusion. Small transformers go in unless the register carries a technical basis for each one left out.
- Motors 50 hp and smaller ignored: do not delete them — aggregate them. Lump each bus's small motors into a grouped contribution and state in the register whether motors were lumped by bus or modeled individually.
Does load-flow analysis belong in the arc flash scope? #
No — load flow answers voltage drop and equipment loading, and none of its outputs feeds the arc-flash calculation, which runs on impedances, source fault data and clearing times, so buy it only as a separate, optional deliverable. It earns its cost when transformer loading or feeder voltage drop is a question you need answered anyway. Scope it separately, with its own loading-assumption register, and keep it out of the arc-flash price.
What do we do about a 35 kA breaker the model shows at 38 kA? #
Treat it as an overduty condition now: NFPA 70, the National Electrical Code, 2023 edition, requires in 110.9 that interrupting ratings meet or exceed the current available at the line terminals, and a 35 kA rating carries no hidden safety factor. Your 38 kA has the shape of an infinite-bus screen, and that is checkable arithmetic. Hypothetical example with every input stated: a 2,500 kVA transformer, 480 V secondary, 8 percent impedance (assumed for this example — the nameplate governs), infinite primary source.
- Full-load current = 2,500,000 VA ÷ (1.732 × 480 V) = 3,007 A
- Bolted three-phase secondary current ≈ 3,007 A ÷ 0.08 = 37,588 A ≈ 37.6 kA
That rounds to the 38 kA you are carrying, which tells you the figure likely ignores utility source impedance and the conductor between transformer and breaker. Both move the duty, usually downward, but by how much is not guessable: get the utility's available fault current at the service, or its source impedance with X/R, in writing, and recalculate. Keep the infinite-bus case in the report as the withstand screening case, and confirm the breaker's exact interrupting rating and the voltage it applies at before comparing. The calculated duty is an estimate until checked against the governing code and the equipment documentation; confirm local application with the authority having jurisdiction.
The decision, case by case:
- Verified duty at or below 35 kA at the rated voltage: document the utility basis and close the finding.
- Verified duty above 35 kA: the breaker is replaced or the available fault current is engineered down; a licensed electrical engineer decides and signs it.
- Until one lands: the finding stays open and the board is handled as overduty.
Grandfathering is not an argument here — interrupting capability is a physical limit of the installed breaker, and the fault current the utility delivers today does not care which code edition the plant was built under. During the wait, hold interaction with that switchboard to normal operation, lock out and test for absence of voltage before anyone opens a panel or terminal compartment on it, and route switching that cannot be avoided through the incident-energy controls and protective equipment your program sets — the discipline behind what PPE operators need to switch 480 V MCC disconnects. Close the 3 kA gap, about 9 percent over the rating, on data rather than on a schedule.
What deliverables and acceptance checks close the project? #
Ten items close it: the editable ETAP project file, updated one-line, input-data register, utility-data basis, short-circuit results, time-current curves, coordination exceptions, arc-flash results and labels, the exclusion register, and the open-assumptions list. IEEE 1584.1-2013 exists to define exactly this — what an arc-flash study must specify and hand over — so cite it in the scope as the deliverables anchor.
Require in your ETAP revision:
- Editable project file with a revision number, running end to end under your license
- Short-circuit results for every operating configuration
- Time-current curves for every in-scope path, or the group map covering it
- Coordination exceptions, each explained
- Labels carrying incident energy, arc-flash boundary and working distance
- Exclusion register and open-assumptions list
Before final acceptance:
- Your own staff run the model end to end, not just the contractor's
- Every analyzed bus names its clearing device, and any case where an upstream device clears is explained
- Every radial path maps to a reviewed curve or appears on the omission list
- Each exclusion passes the written criterion in its register entry
- The 2,500 kVA transformer and 800 A breaker case is recalculated with utility data and closed by a licensed electrical engineer
Questions asked
Is one time-current curve per switchboard enough for the whole board?
Only when the omitted paths match the studied one in breaker frames, trip settings and conductor sizes and lengths — then one curve represents the group. Otherwise each unique path needs its own curve. Require the report to map every feeder and branch path to a reviewed curve or list it as unverified, so nothing on the one-line inherits a result it did not earn.
Is there a safety factor built into a 35 kA interrupting rating?
No. The interrupting rating is the maximum available fault current the breaker is rated to interrupt, stated at a specific voltage; the same frame can carry different ratings at different voltages, so read the nameplate before comparing. A verified 38 kA against 35 kA is 3 kA over the rating, about 9 percent, and it stays an overduty finding until utility data lowers the duty or the breaker is replaced.
Who should review and sign the finished study?
Write it into the scope: a licensed professional engineer experienced in power-system studies reviews the model, the assumption register and the arc-flash results, and seals the report where your jurisdiction requires sealing. The same engineer closes the overduty case on the 800 A breaker, because that decision changes equipment. Data collection can be done by technicians; acceptance is an engineering signature.
How do we keep the ETAP model maintainable after handover?
Require the editable project file with a revision number and the input-data register, not just PDF reports, and have your own staff run a study end to end before final acceptance. Afterward, update the model whenever a breaker setting, transformer or feeder changes, then re-run short circuit and arc flash before anyone re-labels equipment — a stale model produces confident, wrong labels.