Explainer
Will power meters reboot during a changeover supply transfer
Short answer
Yes — under an open-transition changeover, plan on a reboot. The meter sees release time, dead time, pickup time and contact bounce as one gap, commonly near 200 ms on a generator transfer, against the 100 ms ride-through reported for the PM8000 series. Feed meter control power from a UPS or station battery unless the measured worst case stays at or below 70 ms.

On this page
- Why would a power meter reboot during a changeover supply transfer?
- How long is the interruption at the meter terminals?
- How much ride-through does the meter actually have?
- Do the IEC 61000-4-11 test passes prove the meter survives the transfer?
- How much margin should the design carry?
- How do I measure the interruption at the meter terminals?
- When should I feed the meters from a UPS or station battery instead?
- Should breaker charging motors share the meter control-power branch?
- What is the decision?
- Questions asked
Yes — under an open-transition changeover, plan for a reboot unless you can prove otherwise. The meter's control-power terminals see one continuous gap built from relay release time, deliberate dead time, pickup time and contact bounce, and on a generator transfer that total commonly lands near 200 ms, roughly twice the 100 ms ride-through reported for the PM8000 series. The immunity tests listed on the datasheet do not change that conclusion. This article gives you the timing arithmetic, the measurement method and the decision rule, and it ends with the supply architecture that removes the problem.
Why would a power meter reboot during a changeover supply transfer? #
An open-transition changeover is break-before-make: the transfer device opens the outgoing source before the incoming one closes, so the meter's control-power terminals see the relay release time, the deliberate dead time, the pickup time and contact bounce as one continuous interruption rather than a brief notch. Transfer-switch documentation describes open transition this way precisely because the two sources are never paralleled. In a three-source scheme selecting between a transformer, a generator and a UPS-backed feed, the sources are not synchronized with each other, so open transition is the default and the gap is by design, not a defect. A meter's power supply has some internal hold-up, but a complete zero-voltage interval lasting tens or hundreds of milliseconds outruns it. What decides the reboot is the longest complete interruption at the meter terminals, not the relay's headline switching speed.
How long is the interruption at the meter terminals? #
Add four intervals — contact release time, the dead time programmed into the transfer scheme, incoming contactor pickup time and contact bounce — and for a typical automatic open transition onto a generator the sum lands near 200 ms, about twice the meter's ride-through. Generator transfer dead times are commonly set at hundreds of milliseconds on purpose, to let the incoming source build stable voltage before the load lands on it. The relay's own mechanical speed is only one of the four terms.
Worked example (illustrative settings, not any relay's guaranteed data):
- Contact release time: 20 ms
- Programmed dead time: 150 ms
- Incoming contactor pickup time: 30 ms
- Contact bounce: 5 ms
20 ms + 150 ms + 30 ms + 5 ms = 205 ms
At 205 ms, a meter in the 100 ms class reboots every time. Even a genuinely fast scheme that lands at 80 ms leaves only 20 ms of allowance. Get release, dead, pickup and bounce figures from the transfer device's documentation at your operating conditions, then measure — the next sections give the method.
How much ride-through does the meter actually have? #
Work with 100 ms as the reported ride-through for the PM8000 series, and confirm the figure in the technical data for the exact catalog number on each nameplate before you sign off a design. The series documentation lists a supply range of 90...415 V AC at 45...65 Hz with ±10% tolerance, and 110...415 V DC with ±10%. Those steady-state ranges prove the meter can run, not how long it can bridge a gap — an input sitting happily inside the AC range says nothing about the transfer interval. The 100 ms figure circulates as a reported value for the family; the value for your meter is whatever its own bulletin states. Models differ: a PM8240 and a PM5341 are different meters with different documents, and METSEPM8210 is identified as the variant with low-voltage DC control power instead of AC. Record the catalog number, the input ranges and the documented ride-through for every meter in the panel before comparing anything with the changeover timing.
Do the IEC 61000-4-11 test passes prove the meter survives the transfer? #
No — IEC 61000-4-11 is the voltage dips and short interruptions immunity test at defined severities and durations, and a pass shows behavior under those laboratory levels only, not under a real changeover whose gap is longer or different in shape. Read the test levels and durations from the meter's own declaration, at the edition it cites, and compare the declared zero-voltage test duration directly with your measured gap. The electrical fast transient test (IEC 61000-4-4) and the surge test (IEC 61000-4-5) address bursts and transients, not a sustained interruption at all. If your measured interruption is 205 ms and the declaration's most severe interruption test runs for a shorter defined duration, the test result simply does not cover your event, and you cannot claim it as evidence the meter rides through.
How much margin should the design carry? #
Design to 70 ms: accept a changeover-fed meter only when the measured worst-case interruption stays at or below about 70 ms, a 30 percent margin against the reported 100 ms, because a measurement just under the limit leaves nothing for tolerance, temperature, aging or relay replacement. The arithmetic is 0.7 × 100 ms = 70 ms.
A measured 80 ms gap passes numerically and fails in practice. What eats the margin: control-power input sitting at the low end of its range, a cold cabinet, contacts worn enough to slow release, the supply loaded to its stated burden, and the next relay you buy having different timing from the one you measured. Margin is also why the measurement must be the worst case across every permitted source pair and both directions, not the best of several attempts.
How do I measure the interruption at the meter terminals? #
Capture the voltage waveform directly at the meter's control-power terminals during every permitted transfer, with an instrument and probes rated for the installation's voltage and fault-energy environment, and measure from the moment voltage leaves the meter's valid operating region until it returns and stays there. Before you open any panel or terminal cover for this work, de-energize, lock out and test for absence of voltage as NFPA 70E, 2024 edition, requires; make the live capture only under the precautions your arc-flash study sets for that equipment, and confirm the approach with the authority having jurisdiction.
Then: capture the instantaneous waveform or a high-resolution event record — a slow RMS trend hides a complete interruption entirely. Repeat for each source pair and each direction, including transfers while breaker charging motors are running if that is a permitted system state. Check the incoming source's frequency against the 45...65 Hz range before the relay connects it. Watch the meter's communications and event log at the same time; a reboot writes itself into that log as a power-loss event, which corroborates the waveform capture.
When should I feed the meters from a UPS or station battery instead? #
Feed meter control power from a dedicated UPS or the station battery whenever the measured worst case exceeds about 70 ms — which every open transition onto an unsynchronized generator will — and keep the breaker charging motors off that branch. Decide from the measured interruption, never from an assumed relay speed:
| Measured condition | Decision |
|---|---|
| Worst case at or below about 70 ms across every transition | Keep the changeover feed, retest after any relay replacement |
| Worst case near or above the ride-through figure, as in the 205 ms example | Dedicated UPS or station battery on the meter branch |
| Station battery present and the exact meter accepts DC | Feed the meter directly from the battery inside its DC input range |
| AC-only meter plus a battery | UPS or a listed inverter stage between battery and meter |
For the direct battery feed, the series documentation lists 110...415 V DC with ±10%; check float and equalize voltages against that window, including equalize. For an AC-only meter the conversion stage is the same sizing exercise as in sizing a step-down transformer for a 110 V UPS. Decide the grounding of the new control-power secondary deliberately; the trade-offs are set out in grounded or floating control power transformer secondaries in MCCs. Size the no-break source by summing each meter's stated control-power burden plus displays and communications gear, with margin. Any power-monitoring display at the switchboard shares the same exposure, so where the computer is built into the display, an industrial panel PC belongs on the same no-break branch as the meters. Coordinate branch protection so a fault on one meter branch does not remove control power from every meter in the panel.
Should breaker charging motors share the meter control-power branch? #
No — put spring-charging and other motor loads on a separate branch, because a motor that restarts through the transfer draws inrush that holds the shared bus low and can keep the meter terminals below the valid operating region even after the incoming contactor closes. The exception is a backup source deliberately sized for that motor starting demand; a small metering UPS is not. Separating the loads also means a charging-motor fault or a long recharge cycle cannot take the metering record down with it, and the UPS sees a flat resistive-ish burden instead of a motor start it was never sized for.
What is the decision? #
Assume the meter reboots, then prove otherwise: for any open-transition transfer the realistic terminal gap approaches or exceeds the ride-through, so the default design is a dedicated UPS or station battery on the meter control-power branch, with relay speed treated as irrelevant to the decision. Case by case:
- Closed transition between sources permitted to run in parallel: the gap is eliminated, but this is only legitimate with a synchronism check between sources that may be paralleled. Never make-before-break a generator against the utility. Even then, verify the meter sees no sag below its valid operating region.
- Open transition with a measured worst case at or below about 70 ms against the reported ride-through: keep the changeover feed, and retest after any relay replacement.
- Everything else, including any open transition onto an unsynchronized generator: UPS or station battery on the meter branch.
Close the job in commissioning: execute every permitted transition in both directions under representative auxiliary load, verify no reboot, no communications loss, and no gap in the energy log beyond the expected dead interval.
Questions asked
Does a closed-transition changeover remove the reboot risk?
Yes, when it is allowed. A closed or make-before-break transfer overlaps the two sources briefly, so the meter terminals see no gap at all. It is legitimate only between sources that are synchronized and permitted to run in parallel, such as two utility feeds; never parallel a generator with the utility through make-before-break.
Is the 100 ms ride-through value the same for every meter model?
No. That figure is reported for the PM8000 series; other families document their own values, some in milliseconds and some not at all. Read the technical data for the exact catalog number on each nameplate, and never carry a series value across to a different meter family or a DC-powered variant without checking.
How do I size the UPS or battery branch for the metering panel?
Read the control-power burden in volt-amperes from the technical data for each meter and display on the panel, add the communications equipment, and size the no-break source with roughly 30 to 50 percent margin. Keep breaker spring-charging motors off that branch unless the source is deliberately sized for their inrush.
Will logged energy data survive the transfer?
Expect a gap. Even where a meter keeps configuration and history in nonvolatile memory, the measurements taken during the zero-voltage interval are missing from the record, and many meters write a power-loss event to the log. Check the model documentation for what persists through a control-power loss and review the event log after each commissioning transfer.
Can I just use a faster changeover relay instead of a UPS?
You can, but only with proof. Measure the complete terminal-level interruption across the relay's rated operating conditions; if the worst case keeps a comfortable margin below the meter's documented ride-through, the meter stays up. A fast headline transfer time does not establish that by itself, because dead time and contact bounce dominate the total.