Where conduits enter a dry type transformer on a concrete pad

Power distribution and transformers Published 7 min read By Current Intel engineering team

Short answer

No National Electrical Code article forces transformer feeder conduits through the pad concrete; the certified outline drawing decides, because the raceway must land at the terminal box or entry plate the manufacturer provides. Entry inside the footprint: stub through the slab. Entry on a side face: rise beside the pad and keep the datasheet bending radius between stub and entry; missing drawing: hold every stub-up.

On this page
  1. What the National Electrical Code requires
  2. Read the certified outline drawing first
  3. The route each entry position takes
  4. The bending radius check that passes or fails a side stub
  5. Sealing, corrosion and ventilation at a chemical plant pad
  6. Setting and proving the stub-ups
  7. The decision
  8. Questions asked

No National Electrical Code article forces the feeder conduits of a dry type transformer to rise through the pad concrete. The route is decided by the unit's certified outline drawing: the raceway has to end at the terminal box or entry plate the manufacturer built into the enclosure, and only that drawing tells you where it sits. If the entry is inside the enclosure footprint, the conduits stub through the slab. If the entry is on a side face, they rise beside the pad, and the cable datasheet's bending radius decides whether the geometry works. Pour nothing and set no conduit until that drawing is in hand, because a stub-up dimensioned from a generic layout is the usual cause of a field re-route. The checks below turn the drawing into a route decision.

What the National Electrical Code requires #

NFPA 70, the National Electrical Code, 2023 edition, covers the transformer installation in Article 450: guarding, ventilation, overcurrent protection and grounding. Nothing in it tells you where the raceway enters the pad. What the code does govern, wherever the conduits end up: raceways and fittings suitable for the environment, insulation rated for wet service where a buried raceway can hold water, and, where the pad sits inside a classified Class I area, the raceway seals of Section 501.5, which keep vapors and flame from traveling through the conduit. Requirements differ by country, edition and local amendment, so confirm the adopted text with your authority having jurisdiction and with the transformer documentation.

The habit of putting conduit through the pad belongs to pad-mounted liquid-filled units, whose cable compartment sits at the base of the tank, so raceways conventionally rise through a blockout or a vault. That is equipment geometry, not a rule, and a dry type's entry sits wherever its terminal box sits.

Read the certified outline drawing first #

Manufacturers publish a certified outline drawing for each enclosure type and frame size, and the type designation on the nameplate points you to it. The drawing dimensions the enclosure footprint and the terminal box or entry plate for the primary and secondary connections, and it schedules the conduit entry openings: size, quantity and the face each one sits on, side, bottom or top. It also carries the termination clearances you need for forming conductors at the lugs.

Take the entry position from that drawing and dimension each stub-up to two pad corners, not to the duct bank or a previous job's template. If the drawing for the ordered unit has not been issued, stop all stub-up work and request it. A generic dimension sheet for a similar frame is the document that ends with conduit cut out of a finished slab.

The route each entry position takes #

Entry position on the drawing Route What it commits you to
Bottom plate inside the footprint Stub through the slab, in an adjustable blockout or sleeve under the plate Conduits plumb under the entry, ends capped until the pull
Side opening on the terminal box face Stub beside the pad, rising to the entry height on a sweep Slab stays unpenetrated, and the bending radius check below must pass
Top opening Raceway rises beside the enclosure on strut to the top No stub position to set; keep the run clear of the ventilation openings
Entry not shown, or drawing not issued Hold every stub-up and request the certified drawing No conduit, sleeves or cuts to final position

The side and top routes leave the slab intact; only the side route depends on the bending radius check below.

The bending radius check that passes or fails a side stub #

Minimum bending radius is the smallest radius a cable may be bent around without damaging its conductors or insulation; the cable manufacturer's datasheet states it, normally as a multiple of the overall diameter. A 90-degree change of direction consumes one radius of straight run, so a side stub has to clear two checks: enough height above the pad for a full radius before the first bend, and enough horizontal offset from the stub centerline to the entry opening to cover another radius.

Worked example, with every input an example value: a 1500 kVA dry type with a 15 kV primary, fed with shielded medium-voltage cable whose datasheet lists an overall diameter of 1.30 in and a minimum bending radius of 12 times that, so 12 x 1.30 in = 15.6 in. The certified drawing puts the side entry opening 28 in in from the pad edge, and the planned stub stands 6 in clear of that edge and 24 in tall.

  • Vertical check: 24 in of straight stub above the pad clears the datasheet radius before the first bend, so it passes.
  • Offset check: 28 in - 6 in = 22 in from stub centerline to opening, against the datasheet radius; it passes and leaves 22 in - 15.6 in = 6.4 in of straight run before the cable enters.

Decision for this example: the side stub works. Had the drawing put the opening 20 in in from the edge, the offset would be 20 in - 6 in = 14 in, under the datasheet radius, and the cable would kink at the entry; the fix is to move the stub inboard through a blockout until the offset clears the radius, or to give that opening its penetration through the slab. Run your own numbers the same way: drawing position minus stub position, against the datasheet radius, and both checks have to pass.

Sealing, corrosion and ventilation at a chemical plant pad #

Both routes bring the raceway into the enclosure interior, so where the stub rises matters less than how it is sealed. A buried raceway is a path for water, and in a chemical plant for process vapors as well. Where the pad sits in a classified Class I area, the sealing requirements named above apply, and the plant's classification drawings decide whether that is your pad. In an unclassified location, seal every conduit end after the pull against water and vapor, and keep wet-location rated insulation and fittings in the buried run.

Choose the conduit material from the plant's corrosion specification: an exposed side stub breathes the plant atmosphere for its whole service life, while slab-embedded conduit is protected but locked in place. Leave the entry pattern as the drawing shows it; a field-cut entry needs the manufacturer's documented approval, because an undocumented cut sits outside the enclosure's published rating.

Ventilation is the third check. A dry type sheds its heat through airflow across the windings, so no raceway, strut or tray may block the enclosure's ventilation openings; the cooling margin at stake is what an evaluation of dry type transformer hot spot temperature rise measures. And the moisture an unsealed stub end carries indoors works the same sweating mechanism described in why idle outdoor dry type transformers sweat and how heaters stop it.

Setting and proving the stub-ups #

Once the drawing and the bending check have picked the route:

  1. Dimension each stub-up from the certified drawing to two pad corners and record the datum; never scale it off the duct bank.
  2. For a slab penetration, form a blockout large enough to allow final adjustment, set the sleeves plumb under the entry plate and cap the ends.
  3. For a side stub, set the height so a full radius of straight run stands above the pad before the first bend, and reach the pad edge on a sweep, not a tight elbow.
  4. Fit bushings on every stub end before the pull so the jacket does not cut on the conduit edge.
  5. Tie or brace the conduit against displacement before the pour or the backfill, then swab or mandrel the raceway to prove it is open before any conductor goes in.
  6. After the pull, seal each end to the classification and corrosion requirements, and confirm no ventilation opening is blocked and no water stands in the enclosure.

Before any terminal box cover comes off to land conductors, the transformer is de-energized on both windings, locked out and tested for absence of voltage with a proven meter; that step comes before every cover you open.

The decision #

Pull the certified outline drawing first, and the route follows it. Entry plate inside the footprint: stub through the slab with an adjustable blockout. Side opening on the terminal box: stub beside the pad, provided stub height and horizontal offset both clear the datasheet bending radius; if the offset fails, move the stub inboard through a blockout or take the penetration route instead. Top opening: raceway up the enclosure side on strut, nothing through the concrete. Drawing not issued: nothing gets set, cut or poured until it arrives. The code never required the penetration; the drawing, the cable datasheet and the seal decide the route, in that order.

Questions asked

How high should a conduit stub-up end above a transformer pad?

End each stub where the outline drawing's entry detail shows. When the drawing gives no height, end the stub so the bushing lands at or just inside the entry plate opening rather than below it, which usually means a few inches above the finished pad. The taller limit is often the cable: the stub must leave a full bending radius of straight vertical run before the cable's first change of direction, and on shielded medium-voltage feeders that radius can exceed a foot.

Can a new conduit entry be field-cut into a dry type transformer enclosure?

Only with the manufacturer's documented approval. A field-cut opening sits outside the enclosure's listing: it can leave the enclosure short of its published ingress rating, and on some designs it lands on a winding compartment wall. Order the entry pattern shown on the certified outline drawing instead, or get the proposed cut approved in writing before the hole saw comes out. An undocumented cut is also something the inspector can make you undo.

What changes when the terminal box entry is on the top of the transformer?

The pad route stops mattering. The raceway rises beside the enclosure on strut or in exposed conduit to the top opening, so nothing penetrates the slab and there is no stub-up position to set. Check that the added raceway run does not block the ventilation openings and that it is supported independently of the enclosure.

Why do liquid-filled pad-mount transformers take conduit through the pad instead?

Their cable compartments sit at the base of the tank, so the raceways conventionally rise through a blockout in the pad or into a vault below grade. It follows the equipment geometry rather than a code rule, and even for those units the manufacturer's outline drawing with its conduit entry schedule is the document that sets the positions.

What can proceed before the certified outline drawing arrives?

Pour the pad itself, and if you want the slab ready for either route, form an oversized blockout near the expected entry zone so it can be trimmed to the drawing later. Hold everything else: no fixed conduit positions, no sleeves cut to final dimensions, no field bends ordered. Once issued, the drawing dimensions the entry against the enclosure footprint, and the stub-up layout follows from it quickly.

Keep reading

  • How-to

    Calculating voltage drop through step-up and step-down transformers

    Yes. A primary voltage drop passes through the turns ratio almost one-for-one in percent — 5% low at 12 kV is 5% low at 480 V — so the study must run every segment from the generator terminals to the farthest branch outlet, combining drops as percentages.

    Power distribution and transformers

  • How-to

    Retapping a 380 V machine transformer for a 240 V supply

    On a 240 V supply, the 208 V primary tap puts the 380 V secondary at 438.5 V, 9.6% over a 400 V machine. Re-tap the primary to the 230 V connection for 396.5 V, and land the fourth wire on protective earth: a three-phase delta feed has no neutral.

    Power distribution and transformers

  • Explainer

    Reverse feeding a step-down transformer on a high leg delta

    Yes — feed the 240 V wye winding from your 240 V 4-wire delta service, leave X0 insulated and floating, take 480 V from the delta and corner ground it. Never tie X0 to the grounded center tap: it applies 0.50 per-unit zero-sequence voltage across windings rated 138.6 V and can circulate 25 per-unit current in a 2% impedance delta.

    Power distribution and transformers