Why a rotary phase converter needs three capacitor banks
Short answer
A rotary converter needs three capacitor banks because they do three jobs: a switched electrolytic start bank of roughly 120 µF per horsepower spins the idler up, film run banks of about 12 and 8 µF per horsepower hold the generated leg, and an optional 4 µF per horsepower bank across the supply corrects power factor. Duty, connection point and size all differ, so one capacitor cannot replace them; size from these rules, then trim by measurement.
On this page
- The three banks and where they connect
- Why the generated leg needs its own run banks
- The start bank: large, brief, switched out
- The run banks: continuous-duty film
- The optional input bank
- Why one capacitor marked 220 V is not the answer
- Sizing the three banks for a 10 hp idler at 220 V
- Commissioning: measure, then trim
- Questions asked
A rotary phase converter carries three capacitor banks because they do three different jobs, and no single capacitor can do two of them. A large electrolytic start bank accelerates the idler from rest and drops out seconds later. Two continuous-duty film run banks hold the generated leg's voltage and phase angle while the converter runs. An optional film bank across the incoming single-phase supply corrects input power factor. Each bank connects between a different pair of conductors, at a different capacitance per horsepower, on a different duty cycle. Once the three jobs are clear, the sizes follow from simple per-horsepower rules.
The three banks and where they connect #
Fix one naming convention for the whole build: A is incoming L1, C is incoming L2, and B is the generated conductor feeding machine L3. The letters name conductors, not standardized motor terminals; confirm the idler's actual connections from its nameplate and connection diagram.
| Bank | Between | Duty | Job |
|---|---|---|---|
| Start bank | A-B, through the start contactor | Seconds per start, then out | Accelerates the idler from rest |
| Run bank 1 | A-B | Continuous | Holds the generated leg in step with A |
| Run bank 2 | C-B | Continuous | Complementary compensation in step with C |
| Input bank | A-C | Continuous when fitted | Corrects supply-side power factor |
The start bank and run bank 1 share a terminal pair but stay separate circuits: different capacitance, different duty, different switching. A start capacitor must never stand in for a run capacitor.
Why the generated leg needs its own run banks #
Single-phase power on two motor terminals produces a pulsating field with no rotation at rest. That is the starting problem, and no amount of run capacitance fixes it. Once the shaft spins, the idler induces voltage on B, but the magnitude and phase angle of that voltage drift with load unless capacitors hold them. Each run bank draws a leading current that pulls the generated leg up in magnitude and swings it toward 120 electrical degrees from the supply phases. Equal banks give the balanced build; a roughly 60/40 split gives the slightly unbalanced build most shops end up with. Neither arrangement produces torque at standstill, which is why a converter in that condition hums instead of starting.
The start bank: large, brief, switched out #
Budget about 120 µF per idler horsepower, ten times the A-B run bank, built from electrolytic cans in parallel. Start capacitors are intermittent-duty parts: on-time is limited, typically to roughly three seconds, with restart limits stated by the maker, so the bank must leave the circuit as soon as the idler is up.
A potential relay does the switching: its coil senses the rising generated-leg voltage, its normally closed contact holds the bank in at rest, and the contact opens at pickup as the idler passes roughly 90 percent of synchronous speed. On a four-pole 60 Hz idler that is about 1620 rpm against 1800 rpm synchronous. Wire the relay from its own datasheet, because the contact can only interrupt so much capacitance: a big idler needs the relay to sense and an auxiliary contactor to break the current.
A drive is the other clean way to bring the idler up to speed before the single-phase supply takes over, covered in feeding a rotary phase converter idler from a VFD.
The run banks: continuous-duty film #
Budget about 12 µF per horsepower on A-B and 8 µF per horsepower on C-B, the 60/40 split. Run banks are polypropylene film capacitors rated for continuous AC duty, commonly marked 370 VAC or 440 VAC, and single cans typically run 2 to 80 µF, so each bank is a parallel combination. Hold 370 VAC as the floor and check the actual voltage across each bank in service, because the generated leg and switching transients can sit above the incoming supply.
The optional input bank #
About 4 µF per horsepower across A-C, film, continuous duty. It supplies reactive current on the single-phase side, so the feeder carries less current for the same real power. It does nothing for output voltage balance; that stays the run banks' job. Decide with instruments: log input current and power factor at no load and at full shop load, and fit the bank only if those readings say the feeder needs relief.
Why one capacitor marked 220 V is not the answer #
The voltage marking is a limit, not a size and not a function. The start bank and the run banks differ by an order of magnitude in capacitance and by duty, one huge and brief, the others modest and continuous, and they sit on different terminal pairs, so one can cannot cover them. The classic one-bank workaround is the self-starting design: roughly 30-35 µF per horsepower between A and B, nothing on C-B, nothing on A-C. It does spin up by itself, but it regulates the generated leg poorly, runs at a poor no-load power factor, and above about 5 hp that no-load reactive current can overload the feeder. One capacitor buys a converter you cannot tune.
Sizing the three banks for a 10 hp idler at 220 V #
Inputs, all from the case at hand:
- Idler: a 10 hp three-phase motor with an unloaded shaft
- Supply: nominal 220 V single phase
- Loads: a mill and a lathe on the generated three-phase output
The rule: size the A-C, C-B, A-B and start capacitances in the ratio 1 : 2 : 3 : 30, with one unit defined as 1 µF per quarter horsepower. One unit on this idler is 4 µF/hp × 10 hp = 40 µF.
The arithmetic:
- A-C input bank: 1 unit × 40 µF = 40 µF
- C-B run bank: 2 units × 40 µF = 80 µF
- A-B run bank: 3 units × 40 µF = 120 µF
- Start bank: 30 units × 40 µF = 1200 µF
Check the split: the A-B bank is 60 percent of the 200 µF total run capacitance, the slightly unbalanced build.
| Bank | Result | Parts |
|---|---|---|
| A-C input, optional | 40 µF | Film, continuous duty |
| C-B run | 80 µF | Film, continuous duty |
| A-B run | 120 µF | Film cans in parallel, continuous duty |
| Start | 1200 µF | Electrolytic cans in parallel, on a contactor |
Decisions:
- Start bank: 1200 µF is about four 270-325 µF, 220 VAC electrolytic cans in parallel, and that is past what a potential relay's own contact should interrupt (the relay-alone cutoff sits near a 5 hp idler's bank), so the relay senses and an auxiliary contactor breaks the current.
- Run banks: 370 VAC polypropylene film minimum, continuous duty, in parallel cans, with the measured voltage across each bank confirming the rating.
- Input bank: leave it out of the first build and add it across A-C only if the measured no-load feeder current crowds the feeder or the starter.
- Stay off the one-bank self-starting design at this size; its no-load current is the feeder overload described above.
Commissioning: measure, then trim #
Before any terminal is touched: open and lock the feeder disconnect, test for absence of voltage, and short every capacitor through a resistor, because the banks sit straight across the lines and hold charge after the supply is dead. NFPA 70E, 2024 edition, requires that verify-before-touch sequence for de-energized work; confirm it with the site procedure and the authority having jurisdiction.
Energize with the machines off and record all three line-to-line output voltages with a true-RMS meter; repeat with the largest motor starting, then running. If B reads high or low under load, move capacitance between the A-B and C-B banks one can at a time and re-measure, aiming for three readings as close to equal as the can sizes allow, with B holding up through the biggest motor start. High no-load current on the idler is normal, as explained in why rotary phase converter idle current is so high; an idler that runs hot after startup is not, and the causes are in why a rotary phase converter overheats after startup. If a machine drops out on the generated leg mid-cut, work through fixing a machine shutdown on a rotary phase converter third leg. When the three voltages stay close through the worst start, the banks are sized; stop there.
Questions asked
Why can't the start capacitor stay connected after the idler is up to speed?
Start capacitors are electrolytic parts rated for brief, intermittent duty; kept in circuit they heat, vent and fail, and the extra capacitance drives the generated leg high and unbalances the idler currents. That is why the potential relay or contactor removes the bank within seconds of pickup, and why the run banks are separate continuous-duty film capacitors sized an order of magnitude smaller.
Do real converters match these per-horsepower estimates?
Close. One published 1 hp converter used 5 µF from one incoming line to the generated leg, 12.5 µF from the other incoming line to the generated leg and about 80 µF for starting, against rule-of-thumb rates of 4, 8 and 12 µF per horsepower with 120 µF per horsepower to start. Every idler and load mix trims differently, and some builders put the larger run bank on the other line, so treat the numbers as a first build and adjust by measurement.
Can I avoid the start bank entirely?
Yes, by spinning the idler some other way. A small single-phase pony motor with a one-way clutch brings it near synchronous speed before the single-phase supply is applied, or a drive ramps it up and is then bypassed. Either way the two run banks are still required, because starting method and voltage balance are separate problems. Never rope-start, foot-start or hand-start an exposed idler shaft.
My generated leg reads low under load. Which bank failed?
Film run capacitors usually fail open, so a generated leg that stays low points to an open A-B or C-B can or a blown fuse in that run circuit. With the converter locked out and every capacitor discharged, measure each can's capacitance and compare it with its marking; replace any that reads far low. If the leg only sags while a motor starts and recovers afterward, the banks are healthy and the split needs trimming, not replacement.