Short answer

Feed L1 to 1/L1 and L2 to 3/L2, jumper the overload relay's T2 output back to contactor terminal 5/L3, and land the motor on T1 and T3 so current passes through two heater elements. Land the factory coil A2 lead on the L2 pole. Bridging L2 to L3 at the line side leaves an empty element and the relay trips or fails to protect.

On this page
  1. Why the line-side bridge fails
  2. Power wiring, step by step
  3. Sizing the feeder for the single-phase current
  4. Control wiring: land A2 on L2
  5. The decision
  6. Questions asked

A factory three-phase IEC starter runs on a 240 V single-phase supply if you wire it in the right order: L1 to 1/L1, L2 to 3/L2, a jumper from the overload relay's T2 output back to contactor terminal 5/L3, and the motor on T1 and T3. The factory blue lead is the coil's A2, and it lands on the L2 pole. Bridging L2 to L3 at the line side instead — the shortcut most often tried first — leaves one heater element dead, and the relay either trips on phase loss or, worse, never senses the motor current at all.

Why the line-side bridge fails #

The thermal overload relay in an enclosed IEC starter carries three bimetal heater elements, one per pole, and its trip mechanism works on differential heating between them. Two things go wrong with a supply-side L2-to-L3 bridge:

  • The middle element carries no current, so the bimetal stack heats unevenly and the differential mechanism opens within seconds, motor connected or not.
  • If the imbalance is small enough at light load, the relay never heats properly. The starter runs, but a stalled rotor or a jam will not trip it. You have removed the motor's only overload protection.

The fix is to put the loop after the relay, so the same circuit current flows through two of the three elements in series. Two loaded elements is what the relay's differential mechanism expects on a healthy two-phase-loaded motor; one loaded and one empty is a fault.

Power wiring, step by step #

De-energize, lock out and tag out the upstream disconnect, and verify absence of voltage with a meter rated for the supply before opening the starter enclosure. NFPA 70E, 2024 edition, governs the energized-work side; confirm the local requirements with your authority having jurisdiction.

  1. Measure the supply at the disconnect: for the single-phase feeder you should read the rated supply voltage between the two hots.
  2. Land the first hot on terminal 1/L1 of the contactor and the second hot on 3/L2. Do not pull a third wire or bridge anything at the line lugs.
  3. Run a short insulated jumper from the overload relay's T2 load-side terminal back to contactor terminal 5/L3. This is the loop. Current now travels L2 into the relay's middle element, out T2, and back through the third pole.
  4. Land the motor's two hot leads on T1 and T3 of the overload relay. T2 stays looped as in step 3.
  5. Torque every lug to the value printed on the contactor's label — on small IEC frames this is typically in the 2.5 to 4.5 Nm range — with a calibrated driver. Loose lugs are the most common cause of nuisance heating in the field.
  6. Set the relay's current dial to the motor nameplate full-load current. A Class 10 IEC bimetal relay trips within 10 seconds at 7.2 times setting, per IEC 60947-4-1; that suits a normal-duty motor. If the load accelerates slowly, fit a Class 20 relay instead.

Sizing the feeder for the single-phase current #

Single phase doubles the current a three-phase motor of the same power would draw, so size the conductors from the motor's single-phase nameplate current, not from a three-phase table. Worked example, all inputs illustrative:

  • Motor: 3 hp, 240 V, single phase, nameplate full-load current 16 A.
  • Branch conductor per NEC Table 310.16, 75 °C column: 125 % of 16 A is 20 A, so 12 AWG copper THHN (rated 25 A) is the minimum.
  • Overload relay setting: 16 A, inside a typical 11–16 A adjustable range.
  • Short-circuit and ground-fault protection: an inverse-time breaker or time-delay fuse sized per NEC Part IV of Article 430 for a single-phase AC motor; confirm the exact maximum with the edition your jurisdiction adopts.

The result is an estimate to check against the governing code edition and the starter's own documentation.

Control wiring: land A2 on L2 #

These starters ship wired for European practice, where control power comes from line to neutral of a three-phase system and blue is the neutral colour. That blue lead inside the enclosure is the coil's A2, factory-routed toward the third line pole. On your single-phase feed there is no neutral, so A2 goes to the L2 pole and the coil sees the full supply across A1 and A2.

Confirm the lead before landing it: with the disconnect locked out, measure continuity from L1 through to the blue wire while holding the START button. A reading in the tens of ohms — a coil of that supply rating commonly reads well under 100 Ω, and one field check measured 280 Ω on a small frame — identifies it as the coil return; a dead short does not. Then land it on the L2 pole, re-energize, and press START: the contactor should pull in cleanly and the relay should hold its reset.

If you are also feeding a control transformer or drive line-up on this panel and need a display or logging computer at the enclosure, an industrial panel PC is the unit that combines the screen and computer in one enclosure-rated package.

The decision #

  • Loop T2 to 5/L3 after the relay, motor on T1 and T3: correct, protected, done.
  • Bridge L2 to L3 at the line side: the relay trips on phase loss at load, or silently loses overload protection — rewire before running.
  • Blue A2 lead floating: coil will not pull in; land it on L2 after the continuity check.

For a refresher on landing the coil and seal-in contacts on a plain contactor, see wiring a three-pole contactor for a single-phase motor, and for the relay's other side of the circuit see wiring overload relay contacts to the coil and the PLC. Setting the dial is covered in setting overload relays from motor nameplate full-load current.

Questions asked

Why not just bridge L2 and L3 at the line terminals?

A bridge at the line side splits the current before it reaches the overload relay, so one heater element carries little or no current and the other two see only part of the load. The relay reads that asymmetry as a lost phase and trips, or in a light-load case never heats enough to protect the motor. The loop must be made after the relay: T2 back to 5/L3, not L2 to L3 at the line lugs.

What does the blue wire in the enclosure connect to?

On these IEC enclosed starters the blue conductor is the factory A2 coil lead, routed to the third line pole because European practice derives control power line-to-neutral with blue as the neutral colour. Confirm it with a continuity check from L1 through the held START button, then land it on the L2 pole so the coil sees the full 240 V across L1 and L2.

What trip class should the overload relay be set to?

Most IEC bimetal relays are Class 10: they trip within 10 seconds at 7.2 times the setting current, per the trip-class definitions in IEC 60947-4-1. That is right for a normal-duty motor. For a long-acceleration load pick a Class 20 relay instead, and set the current dial to the motor nameplate full-load current.

Does the looped wiring still give real overload protection?

Yes, if the loop is made after the relay and the setting dial matches the motor. Two of the three elements carry the full motor current, which is enough for the differential trip mechanism to act. The danger case is the un-looped bridge: the motor runs fine but the relay never senses the load, so a stalled rotor or jam will not trip it.

Keep reading

  • Troubleshooting

    Why a three-phase motor starter trips on a repeatable schedule

    A trip that repeats on the same schedule is an event you can capture: check the motor dead, then watch the meter and the relay flags at the moment of the stop and classify it as an overload trip, a phase-protection dropout, a latch drop or power at the motor with no run. In the confirmed case this pattern came from, the cause was a short damaged wire segment in the starter switch, and the motor was fine.

    Motors and motor starters

  • How-to

    Wiring a three-pole contactor for a single-phase motor

    Run the single-phase current through two poles in series per the overload maker's diagram — supply to terminals 1 and 5, a link between 3 and 6, motor leads at 2 and 4 — and never parallel all three poles. Set the overload at 125% of the 6 A nameplate full-load current (7.5 A) when the service factor is 1.15 or higher or the temperature rise is 40 °C or less, otherwise 115% (6.9 A), per NFPA 70 (NEC) 430.32.

    Motors and motor starters

  • Troubleshooting

    Why neutral-side switching trips a smart DOL starter

    Move the direction changeover contactor to the line side so the starter feeds the selected winding directly, and leave the run capacitor between the CW and CCW terminals: in the tested 110 V, 2.6 A circuit that raised successful starts from about 1 in 20 to 19 in 20. Return-side switching lets capacitor charging current through the unselected winding distort the current the starter measures at closure, so its residual-current diagnostic reports a missing path.

    Motors and motor starters