How-to
Setting motor undervoltage auto restart timer groups
Short answer
Keep the existing 6-second TD1 off-delay and 0.6-second TD2 on-delay on both groups. Do not add 10 seconds to Group B's timers: a longer timer only proves time passed, not that the 323 kW forced-draft fan reached speed. Release Group B from a verified at-speed condition and stagger motors 6 to 10 seconds apart as the motor-starting study confirms.
On this page
Keep the existing settings on both groups: TD1, the off-delay timer that holds the auto-start contact, stays at 6 seconds, and TD2, the on-delay timer in the contactor start path, stays at 0.5 seconds is wrong — it stays at 0.6 seconds. Do not add 10 seconds to Group B's timers. That change stretches the restart window to 16 seconds, letting motors restart after outages the scheme was built to block, and a 10.6-second TD2 proves only that time passed — not that the 323 kW forced-draft fan leading Group A reached full speed. Release Group B from a verified completion condition instead: an at-speed permissive from the fan, with starts staggered 6 to 10 seconds apart as the motor-starting study confirms.
What the two timers actually control #
TD1 and TD2 do different jobs, and neither one is a group sequencer.
| Timer | Type and job | Setting |
|---|---|---|
| TD1 | Off-delay: holds the auto-start contact closed through a control-supply interruption | 6 s |
| TD2 | On-delay: delays contactor pickup once the start path is restored; wired to bypass the seal-in contact | 0.6 s |
The TD1 setting is a restart window, not an acceleration allowance. Control power back inside that window: the on-delay path completes, its contact closes within 0.6 s, and the contactor energizes through the TD2 permissive. Control power gone longer: TD1 opens, the auto-start path breaks, and the motor stays stopped until someone restarts it. That blocking is deliberate — it prevents unattended restarts after a genuine outage.
One discrepancy to settle first: the scheme as described calls the 0.6-second on-delay "TD1" in one place and makes TD1 the six-second off-delay elsewhere. Trace the schematic and identify each timer by device tag, coil, contacts and terminals; a naming conflict is never resolved by assumption.
Why adding 10 seconds to both timers is the wrong fix #
Two independent failures.
TD1 at 6 + 10 = 16 s changes what the scheme blocks. Every Group B starter would auto-restart after control-supply interruptions up to 16 s, and the band between the original window and the new one is precisely what the scheme excludes. Whether those restarts suit the process is a protection question the timer change answers silently.
TD2 at 0.6 + 10 = 10.6 s starts Group B a fixed 10.6 s after control power returns, whatever the fan is doing. A 323 kW forced-draft fan is a high-inertia load: its acceleration time depends on the motor and fan torque curves and on bus voltage during the restart, and torque falls with the square of voltage, so a depressed bus lengthens the start. Neither 15 s nor 20 s is a rating you can look up — both are guesses. If the fan needs longer than the delay, Group B closes while the fan still draws starting current, recreating the simultaneous-restart condition the study rejected when it found unacceptable voltage drops on downstream buses. Long acceleration also stresses the overload relay, which is set separately from any restart timer — see setting overload relays for high-inertia starts.
Structurally, two per-motor timers do not make a group interlock. Group B needs a defined start point, a verified completion condition from Group A, and defined behavior when a Group A motor fails to start or trips.
How to set the grouped restart scheme #
- Open nothing energized. NFPA 70E, 2024 edition — the standard for electrical safe work conditions, including lockout and testing for absence of voltage — governs before any MCC bucket or terminal compartment is opened; follow your site program and the equipment documentation.
- Trace and tag. Identify both timers by device tag, coil, contact and terminal on the drawing. Confirm which contact maintains auto-start and which bypasses the seal-in.
- Leave Group A alone. Keep the settings as found in the table above. The study that produced the grouping asked for sequencing, not longer windows.
- Release Group B on a verified condition. Best is an at-speed contact or speed switch on the 323 kW fan. Next best is acceleration-complete detection in the multifunction motor protection relay already in the starter — current settled near the full-load value is the usual signature.
- Put the sequencing in one place. If the protection relay supports restart programming, do the grouping, the stagger and the failure handling there rather than across hard-wired timers. Motor management systems of this class pause the restart delay for the duration of a dip and cancel a delayed restart when a start or stop command arrives — verify that documented behavior for the relay model and firmware installed.
- Stagger within each group. Space contactor commands 6 to 10 s apart, as far as the study's bus-voltage results accept. Four motors at the shorter gap span 18 s from first to fourth.
- Supervise the transfer. On the open-transition transfer back — and on any future tie closure — hold re-energization until the motor residual voltage on the disconnected bus has decayed; a bus residual undervoltage relay, device 27R, supervising closure is the standard arrangement, and the effect of closing the bus tie on motor starting shows what unsupervised closure does. The voltage check behind all of this is the same calculation as estimating voltage sag from motor inrush current.
- Commission and record. Measure the fan's acceleration under representative bus voltage, set any fallback delay above that measurement with margin, and document the observed sequence — including what each group does when a motor trips during the restart. All motors are rated for auto-restart duty, so motor capability is not the limit; bus voltage during the grouped restart is.
Timing Group B release for a 323 kW forced-draft fan on a 4.16 kV MCC #
Inputs:
- Five 4 kV motors per MCC with time-delayed auto-restart; four MCCs, fed through two 13.8/4.16 kV transformers on each 13.8 kV bus (plant single-line).
- Largest Group A motor: 4 kV, 323 kW forced-draft fan, high inertia (motor nameplate and study).
- Existing timers: the off-delay and on-delay settings listed in the table above (starter scheme description).
- Proposal under review: add 10 s to both Group B timers.
- Study finding: restarting every auto-restart motor at once produced unacceptable voltage drops on particular downstream buses (motor-starting study).
Rule in words: Group B is commanded only when Group A is complete — its last motor at speed, proven by a permissive — and inside each group the contactor commands are spaced by the study's stagger.
Arithmetic:
- Group A span, four motors, shortest accepted stagger: (4 − 1) × 6 s = 18 s from the first contactor command to the fourth.
- Proposed Group B TD1: 6 s + 10 s = 16 s restart window.
- Proposed Group B TD2: 0.6 s + 10 s = 10.6 s from control-power return to the Group B contactor command.
Now check the 10.6 s against the job it is meant to do. It counts from control-power return — before the staggered Group A commands have even finished, and regardless of the fan's actual acceleration. Because motor torque scales with the square of voltage, the fan accelerates more slowly on a bus already sagging from Group A starts than at full voltage, and its full-voltage acceleration time is not a nameplate value: it comes from the study's acceleration calculation or a commissioning measurement. The 10 s therefore has no basis that tracks the fan at all.
Decision: keep both timers at their existing values on Group B. Command Group B from the fan's at-speed permissive, and stagger each group by the shortest accepted gap — an 18 s span for four motors — if the study's bus-voltage results accept it. A time-based release is only a fallback, and only when set above the fan's measured acceleration time with margin; a guessed 10 s never qualifies. Confirm the final settings against the approved motor-starting study and the starter and relay documentation.
Questions asked
Should Group B timers be set longer than Group A's?
No. Keep the Group A values unchanged and release Group B from a verified Group A completion condition. Adding ten seconds turns the six-second restart window into sixteen, so Group B restarts after outages the scheme was designed to block, and the resulting on-delay of nearly eleven seconds proves elapsed time, not fan speed.
Is 15 seconds a safe assumed acceleration time for the forced-draft fan?
No. Acceleration of a high-inertia fan is not a nameplate value; it depends on the motor and fan torque curves and on the bus voltage during the restart, and reduced voltage makes it longer. Take the figure from the study's acceleration calculation and confirm it by measurement at commissioning.
Why does a motor stay stopped after a longer control-power outage?
That is the intended timeout, not a failure to issue a start command. TD1's off-delay is the window in which returning control power can re-establish the auto-start path; once it expires, TD1 has opened and blocked automatic restart so the motor does not restart unattended after a real outage.
Can the contactor's auxiliary contact prove Group A reached speed?
No. A closed auxiliary proves the contactor picked up, nothing more. At-speed is proven by a speed switch or at-speed contact on the fan, or by acceleration-complete detection in the motor protection relay, where current settled near the full-load value is the usual signature.