Explainer

What a soft starter simulation needs for a valid result

Motors and motor starters Published 8 min read By Current Intel engineering team

Short answer

A valid soft starter simulation needs the motor entered at its nameplate voltage and connection, the load's real breakaway torque and inertia in its actual starting state, the settings the starter will apply, and each plotted limit read for what it represents. The tool then proposes starters for that one modeled start; trip class 30 in a heavy-start mode describes the overload window, not permission to overload the starter.

On this page
  1. What the simulation solves
  2. Motor data matched to the nameplate
  3. Load torque and inertia in the real starting state
  4. Reading the plotted limits
  5. Worked example: a 55 kW blower start
  6. What the result does not establish
  7. The decision for each case
  8. Questions asked

A soft starter simulation is valid when four things match the real installation: the motor entered at its nameplate voltage and winding connection, the load's actual breakaway torque and inertia in the state it starts, the settings the starter will really apply, and every plotted limit read for what it represents. Get those right and the output — start curves against their limits plus a table of suitable starters — is a sound sizing input for that one modeled start. It proves nothing about repeated-start duty, supply behavior or protection coordination; those stay outside the model. And heavy-start simulation up to trip class 30 describes how long the overload response window lasts, not permission to overload the starter.

What the simulation solves #

A soft starter holds the voltage down during acceleration, and that trade is physics, not a setting. At a given slip, motor torque falls with the square of the voltage ratio while current falls roughly in proportion to it: at 70% voltage a motor delivers 0.70 × 0.70 = 0.49 of its direct-on-line torque and draws about 70% of its direct-on-line current. Lower current buys a longer, hotter start. The simulation integrates exactly this — motor torque minus load torque acting on the total inertia, over the starter's ramp and limits — until the machine reaches speed or stalls. What you enter decides whether that integration describes your machine or a convenient fiction.

What you enter What it fixes The usual wrong entry
Motor: database entry or custom data The torque and current the model produces An entry picked by kilowatt rating alone
Load type, torque curve, inertia Whether and how fast the load accelerates A generic load type instead of the machine's real curve
Starting state: loaded or unloaded Breakaway and acceleration torque An unloaded start modeled for a machine that starts full
Starter settings: initial voltage, ramp, current limit The voltage and current the motor actually sees Settings the commissioning technician will not use

Motor data matched to the nameplate #

Select the exact database entry where one exists, then compare it with the nameplate and datasheet rather than accepting a match on power. The rated current belongs to the stated voltage and connection: the same frame wired for a different connection is a different machine to the model, so match both before trusting any curve. Read the nameplate and connection diagram with the circuit de-energized and absence of voltage verified before any cover comes off.

The database entries are grouped by efficiency class, IE3 and IE4 among them; IEC 60034-30-1 defines those IE efficiency classes for line-operated AC motors, and they say nothing about locked-rotor torque or locked-rotor current — take those two values from the motor datasheet. When the list lacks your machine, recent releases of these tools accept user-defined motors and loads: fill every field from the motor documentation and never borrow locked-rotor data from a nearby size. Note the tool's platform and version with the results you keep, so the record can be reproduced.

Load torque and inertia in the real starting state #

Breakaway torque and acceleration torque are different demands. A fan with an open damper or a loaded conveyor wants more torque at zero speed than its running load suggests, while a high-inertia blower breaks away easily and then takes a long time to spin up. Enter the inertia of everything that rotates — motor, coupling, load — with load inertia through a gearbox referred by the square of the ratio. The machine builder's data is the source; a measured coast-down gives you a check.

Model the state the production start actually uses: damper position, conveyor load, tank level. An unloaded maintenance start is a different simulation. Machines with published torque curves can be specified without any tool, by the method in specifying soft starters for high-inertia blowers without curves; the simulation earns its keep when the curves are missing or the start runs long.

Reading the plotted limits #

Each line on the result graph is a different constraint, and mixing them up misreads the plot. The current limit is what you or the supply allows, and a current-limited start rides it by design. The torque boundary is motor capability against load demand: when the motor's curve touches the load's curve below full speed, acceleration has stopped. The thermal limit is what the motor and starter can absorb during this start. Check the quantity and unit on each curve before calling a crossing a failure.

Trip class is the convention behind the thermal side: at 600% of its set current, a class 10 overload trips within 10 s, class 20 within 20 s and class 30 within 30 s, and at lower currents the thermal trip time lengthens. Reading overload relay trip classes and curves covers what those numbers mean on a real relay. A heavy-start mode that simulates up to class 30 models the start inside the window a class 30 setting allows, and that window belongs to the overload's response. The starter's own heavy-start rating — its documented start time and starts per hour — is a separate number on a separate datasheet, and a start can fit the overload window and still exceed it.

Worked example: a 55 kW blower start #

Hypothetical inputs, typical of a real machine; your motor's datasheet replaces every one of them. Three-phase motor, 55 kW, 400 V, 50 Hz, four poles, 1480 rpm, nameplate current 100 A, direct-on-line values of 600% locked-rotor current and 200% locked-rotor torque. The load is a fan with 100 N·m breakaway torque and 5 kg·m² total inertia, started with the damper partly open. The planned ramp uses 60% initial voltage, and the tool plots average motor torque of 220 N·m against average load torque of 120 N·m during acceleration.

Run the numbers the plot should reproduce:

  • Angular speed at rating: 1480 rpm × 2 × 3.1416 / 60 = 155 rad/s, so rated torque is 55,000 W / 155 rad/s = 355 N·m.
  • Direct-on-line locked-rotor torque: 2.0 × 355 N·m = 710 N·m. At 60% initial voltage the motor produces 710 × 0.60 × 0.60 = 256 N·m, which is 2.6 times the 100 N·m breakaway demand, so the fan breaks away.
  • Direct-on-line locked-rotor current: 6 × 100 A = 600 A; at 60% voltage the model draws about 0.60 × 600 A = 360 A, or 3.6 times nameplate.
  • Net accelerating torque: 220 N·m - 120 N·m = 100 N·m, so the start takes (5 kg·m² × 155 rad/s) / 100 N·m = 7.75 s. This is the hand check described in motor starting time calculation from torque margin and inertia.

Overload check: the class 10 definition point is the set current times six, held for 10 s. This start peaks at 360 A, and thermal trip time grows as current falls, roughly with one over the current squared — the square of 600 / 360 is about 2.8, so the same curve needs roughly 2.8 times longer at 360 A. Even a fast class 10 relay that trips in 4 s at 600 A takes about 11 s at 360 A, and this start clears it. All of this is an estimate: the tool's plotted thermal limit and the starter's documentation decide the final settings.

Three decisions follow. First, keep 60% as the initial voltage: the breakaway margin is comfortable and a higher setting only adds current and heat. Second, set the overload to class 10, because the modeled start finishes well inside that window. Third, the candidate passes the single-start model — its starts per hour at this start time come from the starter's datasheet, not from the plot.

What the result does not establish #

The plot is one cold start. Production starts accumulate heat, so check starts per hour against the starter's documentation and the motor's own starting limits; what NEMA MG-1 start clauses mean for motor start inhibits covers the motor side. Most tools also assume a stiff supply at nominal voltage: the sag a generator or a long feeder causes during the start is outside the model.

The candidate table does not set your protection. The overload is set from the motor nameplate full-load current, the method in setting overload relays from motor nameplate full-load current, and NFPA 70, the National Electrical Code, 2023 edition, covers motor branch circuits including overload protection in Article 430; confirm the requirement with the local authority having jurisdiction and the equipment documentation. The branch-circuit protective device, the supply voltage and frequency match, the bypass arrangement and the starter's cooling and ambient conditions are likewise documentation checks, not simulation outputs.

The decision for each case #

  • The start finishes inside every plotted limit: accept the candidate, then verify starts per hour from documentation.
  • The start finishes but rides the thermal limit: shorten it with more initial voltage or a higher current limit, within what the supply and motor tolerate, or move to the heavy-start case and choose a starter whose documented heavy-start rating covers the longer start.
  • Acceleration stalls, with the motor torque curve meeting the load curve below full speed: the model says this start fails. Raise the initial voltage, start the machine unloaded where the process allows, or the combination is undersized.
  • Production needs frequent starts: the duty check decides, and a candidate that wins the single-start plot can still fail it.

Questions asked

What does the simulation assume about the supply?

Almost every such tool models a stiff source at nominal voltage, so voltage sag during the start sits outside the calculation. Sag costs torque fast, because torque follows the square of the voltage ratio: a 10% dip leaves 0.9 times 0.9, or 81% of the torque, and a start that cleared breakaway with a thin margin can stall. On generator feeds or long cable runs, estimate the dip and rerun the model with that lower effective voltage.

Can one simulation cover several identical motors?

For the single-start curve, yes, when nameplate data, winding connection and starting state genuinely match: same motor entry, same load, same inertia. What does not transfer is duty; each installation's starts per hour, cable length and loaded or unloaded state get checked on their own. Where one starter accelerates several motors in sequence, it carries the accumulated heat of the whole sequence, so simulate the hardest motor and confirm the sequence against the starter's documented duty.

When can you size the starter without a simulation?

When the driven machine has published torque-versus-speed curves and a known inertia, a hand calculation of breakaway torque and starting time gives the same answer the tool would plot, and many fan and pump starts are specified that way. The tool earns its keep for custom load curves, long heavy starts, and whenever a documented candidate table must accompany the specification.

Keep reading

  • Troubleshooting

    Diagnosing a soft starter fault or alarm before resetting it

    Record the exact fault or alarm text, the values shown with it, and whether it appeared during start, run, or stop, before you reset, because a reset clears the diagnostic context. Then check the supply, the starter's documented ratings, the configured motor data, and the load: most trips trace to one of those four, not to a failed starter.

    Motors and motor starters

  • How-to

    Setting a soft starter current limit without overheating the motor

    Set the soft starter current limit from the accelerating torque the load needs, not from the starter's duty figure. Estimate the limit as locked-rotor current times the square root of required torque over locked-rotor torque, check that current, dwell time and starts per hour against the starter's duty table, then verify every start with a measured peak current and acceleration time. At a 300% limit a typical design B motor develops only about a third of its full-load torque.

    Motors and motor starters

  • Troubleshooting

    Soft starter ground fault at crossover points to motor data

    Set the starter's rated motor current to the motor nameplate value (305 A in this case, not the 315 A starter rating) and match the trip class. Ground fault detection and the thermal motor model both calculate from that entry, so one wrong value produces both symptoms.

    Motors and motor starters